Allen ISD has put a price on a districtwide fix for erosion, cracked concrete and worn-out landscaping: about $8.5 million, under a contract that went to the school board for approval Monday night.
The board packet lists a total construction cost of $8,502,903 for what the district calls its Cross District Erosion Control project. That includes a guaranteed maximum price of $8,272,903 from BWC Education Group, the district's construction manager at risk, plus $230,000 in other project costs. BWC collected bids from subcontractors based on plans by RLK Engineering.
The district had not posted the outcome of Monday's votes by midday Tuesday.
What the work covers
The money comes from the 2024 bond. Voters approved $419,062,253 under Proposition A that year, and the district set aside $23,809,658 of it for erosion, landscape, irrigation, foundation and concrete repairs across its campuses.
According to the board memo, this round includes ADA accessibility upgrades, ramp repairs, bus lane repairs, concrete work, irrigation and drainage fixes, and new sod and drought-tolerant landscaping where erosion has become a significant problem.
Grading is the largest single line in the price sheet at about $3.57 million, followed by $1 million for concrete paving, about $640,000 for metal canopies and about $384,000 for storm drainage.
Work would begin once the board signs off, with completion scheduled before the 2028-29 school year starts.