The North Texas Municipal Water District, which supplies Allen, would replace the failed steel wall with cast concrete. The project engineers would cover $376,000 of the cost.

Quincy Vargas· AI-assisted, edited by Jake Team

November 16, 20262 min read

Water treatment facility - illustration, Jake Team LLC

A wall built as part of an upgrade at the North Texas Municipal Water District's Wylie treatment complex partly failed during its first tests, and the district's board is set to approve a $704,669 replacement this week.

The work is part of a $22.4 million project converting the Wylie Water Treatment Plant to biologically active filtration, a process the district says will remove more organic material and produce water less prone to losing its disinfectant as it travels through pipes. Allen is one of the district's 13 member cities, along with Plano, Frisco, McKinney and Richardson.

What went wrong

According to the board memo, a newly built weir wall in a clearwell at Plant III "experienced a partial structural failure" during initial startup and testing. A later structural review found the design would need major changes or a full replacement to work across the system's full operating range.

The original wall used a steel stop-log design. District staff and the project engineer decided a cast-in-place concrete wall would be the more durable fix. The wall controls flow metering of the plant's treated water, which the district uses to pace chemical dosing.

Who pays

Contractor RAVA Construction would do the work under Change Order No. 11. Carollo Engineers and IMEG have agreed to put $376,000 toward the cost, leaving $328,669 to come from the district's regional water system construction funds.

The change order adds 150 days to the contract and brings its total to about $23.5 million, from an original $22.375 million. Ten earlier change orders added about $420,562.

The memo does not say whether the failure affected water service, and it describes no impact on customers.

The district's water committee reviews the change order Wednesday, Nov. 18. The full board meets at 2 p.m. Thursday, Nov. 19, in person and by videoconference. The same agenda includes a $1.49 million engineering contract to design new or replacement shutoff valves at 15 high-priority spots on the district's water transmission system.

Sources

webapi.legistar.com

ntmwd.legistar.com

webapi.legistar.com

ntmwd.com

Share

Quincy Vargas· AI-assisted, edited by Jake Team

Quincy Vargas writes about community life, schools, public safety, and local events in Allen.

Related Stories

More in Texas