Allen ISD plans to rebuild the track and field at Ford Middle School, along with its bleachers and press box, in a project the district values at $7 million.
The district registered the work with the Texas Department of Licensing and Regulation on Thursday, Nov. 5, under the name "Ford MS Renos - Phase 1." State law requires that kind of filing so a registered accessibility specialist can review plans and later inspect the finished work.
According to the registration:
- Location: Ford Middle School, 630 Park Place Drive
- Scope: renovation of the track and field, including bleachers and a press box
- Estimated cost: $7 million, listed as a project using public funds
- Size: 9,848 square feet of work
- Schedule: start Dec. 15, 2026, with completion listed for Aug. 1, 2027
- Designer: VLK Architects of Plano
Those dates would put most of the construction in the spring semester and the summer break that follows.