Olson renovation is 99% done and Curtis and Cheatham are at 94%, while Norton has not started, Allen ISD bond report shows
The district's Sept. 30 construction report, in the trustees' Oct. 26 packet, puts the high school's multipurpose complex at 68% and lists about $180 million spent so far from the 2024 bond.